Project Name: Design, Supply, Installation, Testing and Commissioning for The 15 MWp Electrification of Sabon Gari Market Kano State
Scope of work: the project scope is a Hybrid solar farm consisting of a Hybrid Solar POwer system with 15 MWp PV and 15 MW/15MAWh BESS Lithium-lon Energy Storage with full Eenergy Management systems, and backup Synchronized Systemsof Diesel Generators with a total Capacity of 15 MW using 14 sets of 1100 KVA to cover peak power demand of 7.500kW. the project includes the installation and rehabilitation of existing streetlights and transmission system of cabling and energy.the solar farm is monitored /controlled remotely through Advanced metering infrastructure (AMI) solutions and a high -end SCADA system, and live monitoring is accessible 24/7 through security cameras.Operation and maintenance for 15 years